It is the day you have been waiting for and dreaming about. Anchor Pools is set to begin building your backyard retreat. To make this process as easy and stress free as possible, the following is a step-by-step of making a dream come true.
STEP 1 Layout and Excavation
The
first step is to determine the shape and size of the pool then lay it
out on your property. Once Anchor Pools and the homeowner are
satisfied with the position of the pool, Anchor Pools will remove any
obstacles for construction (i.e., trees, fence, etc.). Anchor Pools will
obtain any and all permits needed to build the pool in compliance with
all building codes and swimming pool standards.
At this point Anchor Pools will bring in heavy equipment to dig your pool. While we will do everything possible to minimize the mess, but you will need to plan to do a little landscaping after pool completion.
STEP 2 Pouring Wall
After
excavation, Anchor Pools will construct the wall of your pool. This
is the backbone to the structure. We do not use a steel wall. Instead
we will pour a 10" concrete wall that has a lifetime warranty.
After we set the forms, place the steel reinforced rebar and install
all fixtures for your skimmers, lights and steps, we will bring in
concrete trucks to pour the wall.
STEP 3 Preparing Walls
Once
the walls have set, Anchor Pools will take the forms down and begin
preparing the wall. We go back over the entire pool to smooth down the
wall in preparation for the liner.
STEP 4 Preparing for the Liner
Our
next step in constructing your pool is to prepare the pool for the liner.
We install a protective wall foam around the perimeter of the pool and
add coping to the top of the wall that the liner fits into. The last
step before dropping the liner is to trial a vermiculite mix into the
bottom of the pool to create the floor of the pool.
STEP 5 Dropping the Liner
Once
the vermiculite has set, Anchor Pools will drop the liner
into the pool. At this point, the pool that you liked in
the picture is beginning to take shape in your backyard.
STEP 6 Preparing the Deck
After the liner is dropped, Anchor Pools will start filling the pool.
While it is filling, we backfill the pool and set up to pour the deck.
STEP 7 Pouring the Deck
Today is the day we put the finishing touches on your pool. Anchor
Pools will bring in concrete trucks to pour the deck.
STEP 8 Ready to SWIM!
After
the deck has set, Anchor Pools will install your ladder and diving board.
Once we add chemicals and clean it for the first time, it is ready for
you, your family, and your friends to enjoy for years to come!
993 ByPass 123 | Seneca, SC 29678 | Ph: 864-882-8311 | Fx: 864-882-8242
Contact Us





